It depends upon who wants it

We’re finally getting to see an update on the quality of life projects that we approved back in 2012.

According to the chart below they have completed 43 out of 129:

qoldec2016

At their rate of four years for 43 projects they will be at this for another 12 years.

They don’t tell us when the rest of the projects will even be started.

The neighborhood Chelsea pool is a tragic example.  Elsewhere in the presentation we learn that it is still in the design phase.

This is a situation where the neighborhood had a swimming pool but the city closed it.  Now years later they still have not replaced it.

On the west side of town a brand new aquatic center is already under construction–right next to an existing pool that still serves the neighborhood.

We deserve better

Brutus

3 Responses to It depends upon who wants it

  1. Chas Thomas's avatar Chas Thomas says:

    Don’t miss the quote at the bottom of the chart…”Delivering Outstanding Services”

    Like

  2. Unknown's avatar Jerry K says:

    A children’s museum isn’t even in the design stage? AAA still trumps STEM.

    Like

  3. Unknown's avatar Annonymous says:

    And by “pre-design” they mean looking for neighborhoods in DTEP to plow under.

    Like