They’re about to do it again.
Item 4.1 on the consent agenda (that’s the one where there is no discussion) of the city council meeting to be held Tuesday, June 16, 2015 is listed as:
There is backup material and it tells us a lot, including:
“The contractor installed the electrical service equipment above ground. This change order will allow for electrical equipment and feeders to be placed below ground.”
Huh?
We should assume that someone at the city was watching as the power equipment was suspended in the air. Now that the work is done we will pay to have the new stuff ripped out and put underground. Were the plans vague? Has the city decided that they now have extra money and they want to upgrade the plaza? Could it be that this change order is a way to funnel more money to the contractor?
More conflict
The backup material indicates that 17 days will be added to the term of the contract. They don’t say whether those are calendar days or are work days or maybe biblical days.
Unfortunately the contractor’s proposal to the city says: “This work will add approximately five weeks to the overall timeframe of the project”. We don’t know if that means 35 calendar days or 25 work days, to say nothing about how we can quantify approximately.
The contractor’s proposal was for $123 thousand. The city’s project manager crossed that amount out and wrote $110 thousand and initialed the change.
The five week extension was not changed. Curious, isn’t it.
See for yourself:
The backup material shows this as change order number 6. One through five must have been doozies.
I guess it would just be to much for us to expect that the city would be precise.
We deserve better
Brutus

Posted by Brutus 

You must be logged in to post a comment.